Plant summary
Scores below are MAI's system-calculated values from the plant record, shown exactly as computed. Eleven process-support assets were documented on site, with nameplate and specification data extracted from photographs and equipment tags.
61
Mechanical Health
Fair — Aging Core Equipment
74
Maintenance Maturity
Documented PM Program
58
Capital Exposure Score
Elevated Capital Exposure
66
Mechanical Risk Score
High — Production-Critical
Five-year capital forecast (system)
$412,000
MAI's modeled exposure for this plant over the next five years. Per-asset Toledo-market replacement estimates are in the capital planning section: the two drivers are the 1998 steam boiler and the 2009 chiller, deliberately sequenced into different budget years and aligned to planned outage windows.
Expected service exposure (system)
$96,000
System-calculated expected service and repair spend over the same window, excluding the capital changeouts in the plan below. Total replacement exposure across all 11 assets reads about $1.18M — the plan only pulls the at-risk portion into the five-year window.
Production criticality
1 SPOF
One single point of failure: Boiler B-1 (1998) carries the full process steam load at peak production. Boiler B-2 (2015) is sized at roughly two-thirds load — enough for sanitation and building heat, not for full-rate production. An unplanned B-1 loss during a production week is a plant-down event, not a maintenance ticket.
The headline story: this plant's mechanical core is older than its maintenance program is good. The PM program is documented and current (Maintenance Maturity 74), which is exactly why the risk is manageable — but documentation doesn't change metallurgy. A 28-year-old boiler carrying process steam as a single point of failure, and a 17-year-old chiller behind it, set the capital agenda. Everything else on the floor is mid-life or newer and stays on PM.
Asset by asset
Nameplate and specification data read from equipment tags photographed during the documentation visit. Anything a tag didn't state — or that couldn't be read — is marked as such rather than filled in. Ages are manufacture year against the current year (2026).
B-1 — Cleaver-Brooks firetube steam boiler
AST-I001 · Boiler room · Serves: Process steam header — full plant · Status: Operating
Replace — plan now · 28 yrs · Single point of failure
| Nameplate / spec data |
| Manufacturer | Cleaver-Brooks |
| Model | CB-LE 200-150-150 (firetube, 4-pass) |
| Serial | OL-104482 |
| Manufacture year | 1998 |
| Age | 28 years |
| Fuel | Natural gas (dual-fuel oil backup, disconnected 2019) |
| |
| Capacity | 150 boiler HP · 5,025 MBH output · ~5,175 lb/hr steam |
| Design pressure | 150 psi steam |
| Burner | Low-NOx, linkageless controls retrofit 2014 |
| Last internal inspection | 2025 — passed; tube sheet ligament cracking noted as watch item |
| Read confidence | 88 / 100 |
| Service & PM details |
| Burner service | Low-NOx burner — nozzle/diffuser assembly, flame rod, and ignition electrode inspected and serviced annually; combustion analysis at every PM |
| Gasket kit | Cleaver-Brooks OEM gasket kit (fireside + waterside handhole and manhole gaskets) — renewed at every internal opening; one spare kit held in stores |
| Waterside treatment | Chemical treatment program (sulfite / polymer) — tested weekly and logged in the plant record |
| Safety devices | Operating and high-limit controls, low-water cutoff, and safety relief valve — CSD-1 tested annually; results in Inspections & compliance below |
Recommendation — begin replacement planning now; this is the plant's critical path
B-1 is the single point of failure for process steam. At 28 years — past the typical 25-year planning life for a firetube boiler — with a noted tube-sheet watch item, an unplanned failure during production means the line stops until a rental boiler can be set, piped, and permitted: realistically days, at emergency pricing. B-2 cannot carry full production load (see below). The fix is a planned replacement inside a scheduled outage window, engineered while B-1 is still running. Planning estimate for a like-for-like 150 HP firetube boiler replacement (Toledo market, installed, including rigging, piping tie-ins, stack work, controls, and commissioning; rental boiler bridge during changeout extra): $190,000–$235,000. Start engineering and long-lead ordering in Year 1; target the annual shutdown window.
B-2 — Cleaver-Brooks firetube steam boiler
AST-I002 · Boiler room · Serves: Process steam header — partial load · Status: Operating
No action — monitor · 11 yrs
| Nameplate / spec data |
| Manufacturer | Cleaver-Brooks |
| Model | CB-LE 200-100-150 (firetube, 4-pass) |
| Serial | OL-221907 |
| Manufacture year | 2015 |
| Age | 11 years |
| Fuel | Natural gas |
| |
| Capacity | 100 boiler HP · 3,350 MBH output · ~3,450 lb/hr steam |
| Design pressure | 150 psi steam |
| Burner | Low-NOx, parallel positioning |
| Typical loading | Lead unit off-peak; ~65% of peak plant steam demand alone |
| Read confidence | 94 / 100 |
| Service & PM details |
| Burner service | Low-NOx burner, parallel positioning — nozzle/diffuser assembly and flame scanner serviced annually; O₂ trim verified at combustion analysis |
| Gasket kit | Cleaver-Brooks OEM gasket kit (fireside + waterside handhole and manhole gaskets) — renewed at every internal opening |
| Waterside treatment | Same chemical treatment program as B-1 (sulfite / polymer) — tested weekly and logged |
| Safety devices | Operating and high-limit controls, low-water cutoff, and safety relief valve — CSD-1 tested annually; results in Inspections & compliance below |
Recommendation — no action; routine PM and annual inspection
Mid-life, correctly sized for its role, and the reason a B-1 failure is an outage rather than a catastrophe — it holds sanitation, trace heat, and building heat while production is down. Keep it on annual internal inspection and waterside treatment. When B-1 is replaced, re-evaluate the pairing: a replacement B-1 sized with N+1 intent would retire the single-point-of-failure finding entirely. No capital in the five-year window beyond normal burner and controls upkeep.
CH-1 — Trane CenTraVac centrifugal chiller
AST-I003 · Chiller room · Serves: Process cooling + plant HVAC · Status: Operating
Budget replacement · 17 yrs · R-134a
| Nameplate / spec data |
| Manufacturer | Trane |
| Model | CVHF 0350 (centrifugal, single compressor) |
| Serial | L09K04417 |
| Manufacture year | 2009 |
| Age | 17 years |
| Refrigerant | R-134a · charge ~1,150 lb |
| |
| Capacity | 350 tons nominal · 0.58 kW/ton at full load (rated) |
| Electrical | 460V · 3 phase · starter replaced 2021 |
| Compressor hours | ~61,400 run hours (panel readout) |
| Last eddy-current test | 2024 — tubes within tolerance, 2 plugged |
| Read confidence | 91 / 100 |
| Service & PM details |
| Drive | Direct drive — no belts |
| Refrigerant | R-134a · ~1,150 lb charge — leak-checked quarterly; any charge additions logged in the permanent record |
| Filter-drier | Replaceable-core liquid-line filter-drier — core changed on moisture-indicator or acid-test indication; last changed 2024 with compressor service |
| Compressor oil | POE oil — sample drawn for analysis annually, alongside the tube-test cycle |
Recommendation — budget replacement in years 2–3
Seventeen years and 61,000+ hours is deep into a centrifugal chiller's economic life, and R-134a faces ongoing HFC phasedown pressure — refrigerant cost and availability both trend the wrong way from here. Process cooling rides on this machine: a summer compressor failure means curtailed production, not just warm offices. It doesn't need replacing this year — it needs a funded place in the plan, sequenced after the boiler and matched to a planned outage. Planning estimate for a like-for-like 350-ton centrifugal (or modern low-GWP equivalent) replacement (Toledo market, installed, including rigging, piping, controls integration, and commissioning): $150,000–$190,000. Get the eddy-current test repeated in Year 2 to confirm the window before committing the year.
CT-1 — Marley cooling tower
AST-I004 · Roof yard · Serves: CH-1 condenser water · Status: Operating
Plan refurbishment · 14 yrs
| Nameplate / spec data |
| Manufacturer | SPX Marley |
| Model | NC 8403 (crossflow, single cell) |
| Serial | NC12-88412 |
| Manufacture year | 2012 |
| Age | 14 years |
| Basin | Galvanized steel · coating loss noted at waterline |
| |
| Capacity | 350 tons nominal · 1,050 gpm at 95°F/85°F/78°F WB |
| Fan motor | 25 HP · VFD controlled (added 2018) |
| Fill condition | Original fill — fouling noted on inspection panel |
| Gear drive | Original · oil analysis normal 2026 |
| Read confidence | 86 / 100 |
| Service & PM details |
| Drive | Gear drive with VFD fan motor — no belts; synthetic gear oil sampled annually and changed on analysis |
| Basin & strainer | Suction strainer cleaned monthly; basin sludge vacuumed and waterline coating touched up at spring startup |
| Water treatment | Oxidizing biocide + scale/corrosion inhibitor program — Legionella control plan current and on file |
| Fill & nozzles | Spray nozzles and drift eliminators inspected annually; full fill inspection folded into the years 2–3 renewal below |
Recommendation — refurbish in the same window as the chiller decision (years 2–3)
The tower is structurally sound but its fill and basin coating are at the age where efficiency quietly bleeds: fouled fill raises approach temperature, which raises chiller kW/ton all summer. If CH-1 is replaced, refurbishing the tower in the same outage — fill replacement, basin coating, nozzle and drift-eliminator renewal — protects the new chiller's efficiency from day one. Planning estimate (Toledo market, installed): $18,000–$28,000. If the chiller slips, the tower refurbishment still pays on its own in energy; it just sequences with it for outage efficiency.
AC-1 — Ingersoll Rand rotary screw air compressor
AST-I005 · Compressor room · Serves: Plant air header — base load · Status: Operating
Budget replacement · 21 yrs
| Nameplate / spec data |
| Manufacturer | Ingersoll Rand |
| Model | R110i (rotary screw, fixed speed) |
| Serial | IR05-339812 |
| Manufacture year | 2005 |
| Age | 21 years |
| Drive | Fixed speed · load/unload control |
| |
| Capacity | 100 HP · ~460 cfm at 110 psig |
| Run hours | ~88,200 total · ~71,500 loaded (panel readout) |
| Airend | Original — no rebuild on record |
| Dryer pairing | Shares refrigerated dryer with AC-2 |
| Read confidence | 84 / 100 |
| Service & PM details |
| Intake filter | Panel intake filter element — changed every 4,000 loaded hours or on restriction indication |
| Separator element | Coalescing separator element — changed every 8,000 hours |
| Lubricant | Full-synthetic rotary screw coolant — 8,000-hour change interval; sample analysis at 4,000 hours |
| Drive belts | Belt drive — matched 3-band power band set; tension and condition checked quarterly, set renewed on cracking or glazing |
Recommendation — budget replacement in years 3–4; carry as the plant-air risk
Eighty-eight thousand hours on an original airend is borrowed time, and this machine carries base plant-air load — packaging lines stop without air just as surely as without steam. AC-2 (below) can trim but not carry the full header at peak, so an airend failure is a production event with a rental compressor as the bridge. A modern VSD replacement also cuts the single largest electrical waste in the utility rooms: a fixed-speed machine unloading at partial demand. Planning estimate for a 100 HP-class VSD rotary screw replacement (Toledo market, installed, including piping tie-in and controls): $30,000–$40,000. Sequenced years 3–4, after the boiler and chiller, unless the airend forces the issue sooner.
AC-2 — Kaeser rotary screw air compressor
AST-I006 · Compressor room · Serves: Plant air header — trim/standby · Status: Operating
No action — monitor · 7 yrs
| Nameplate / spec data |
| Manufacturer | Kaeser |
| Model | BSD 75 (rotary screw, VSD-ready) |
| Serial | KA19-55204 |
| Manufacture year | 2019 |
| Age | 7 years |
| Drive | Belt drive · Sigma control |
| |
| Capacity | 75 HP · ~350 cfm at 110 psig |
| Run hours | ~29,800 total (panel readout) |
| Airend | Original — within expected service interval |
| Role | Trim and weekend load; standby during AC-1 service |
| Read confidence | 93 / 100 |
| Service & PM details |
| Intake filter | Intake filter element — changed on Sigma controller hours (4,000-hour interval) |
| Separator element | Separator element — changed every 8,000 hours; differential pressure monitored by the controller |
| Lubricant | Kaeser synthetic rotary screw oil — changed on controller schedule |
| Drive belt | Belt drive — OEM belt; tension and deflection checked at every service |
Recommendation — no action; routine PM
The healthy half of the plant-air pair. Keep it on separator, lubricant, and belt service per the manufacturer's schedule. When AC-1 is replaced, revisit the lead/lag rotation — a new VSD machine should take base load and this unit becomes the trim machine full-time. Replacement is beyond the five-year window; long-range context for a 75 HP-class unit at today's Toledo pricing is roughly $24,000–$32,000 installed.
P-101 — Goulds process pump (condensate return)
AST-I007 · Boiler room · Serves: Boiler feed / condensate return · Status: Operating
Monitor · 18 yrs · Pair with boiler plan
| Nameplate / spec data |
| Manufacturer | Goulds Pumps (ITT) |
| Model | 3196 MTi (ANSI process pump) |
| Serial | GP08-77190 |
| Manufacture year | 2008 |
| Age | 18 years |
| Seal plan | Single mechanical seal · replaced 2023 |
| |
| Capacity | ~180 gpm at 120 ft TDH (duty point) |
| Motor | 15 HP · 460V · 3 phase · replaced 2020 |
| Redundancy | Duplex with P-102 on common skid |
| Condition note | Casing thickness within limits at 2025 UT check |
| Read confidence | 89 / 100 |
| Service & PM details |
| Coupling | Flexible spider (jaw) coupling — elastomer insert inspected at every seal service; laser alignment verified 2020 at motor replacement |
| Filters & belts | None — no filters or belts fitted; condensate tank suction strainer checked quarterly |
| Bearings & seal | Frame bearing oil changed annually; mechanical seal replaced 2023 |
Recommendation — monitor; fold wet-end renewal into the B-1 outage
Eighteen years is old for an ANSI pump but this one is duplexed, its motor is 2020, and its casing passed ultrasonic thickness in 2025 — it is aged, not failing. The efficient move is to price a wet-end rebuild (impeller, wear rings, seals, bearings) into the B-1 replacement outage, when the condensate system is already drained down. Planning estimate for rebuild-in-place (Toledo market): $6,000–$9,000 — a fraction of a nuisance failure during production. Full replacement, if the casing fails its next UT check, plans at $11,000–$15,000 installed.
P-102 — Goulds process pump (condensate return)
AST-I008 · Boiler room · Serves: Boiler feed / condensate return · Status: Operating
No action — monitor · 9 yrs
| Nameplate / spec data |
| Manufacturer | Goulds Pumps (ITT) |
| Model | 3196 MTi (ANSI process pump) |
| Serial | GP17-20855 |
| Manufacture year | 2017 |
| Age | 9 years |
| Seal plan | Single mechanical seal · original |
| |
| Capacity | ~180 gpm at 120 ft TDH (duty point) |
| Motor | 15 HP · 460V · 3 phase · original |
| Redundancy | Duplex with P-101 on common skid |
| Condition note | Vibration within ISO limits at 2026 route check |
| Read confidence | 92 / 100 |
| Service & PM details |
| Coupling | Flexible spider (jaw) coupling — elastomer insert inspected on the vibration route; alignment checked at seal service |
| Filters & belts | None — no filters or belts fitted; condensate tank suction strainer checked quarterly |
| Bearings & seal | Frame bearing oil changed annually; original mechanical seal — monitored on route |
Recommendation — no action; routine PM
The younger half of the duplex pair and the reason condensate return is not on the risk list despite P-101's age. Keep both pumps on the vibration route and rotate lead weekly per the PM program. No capital in the five-year window.
P-103 — Armstrong process pump (chilled water)
AST-I009 · Chiller room · Serves: CH-1 primary chilled water loop · Status: Operating
Verify at next outage · Age unknown
| Nameplate / spec data |
| Manufacturer | Armstrong Fluid Technology |
| Model | Not readable — tag corroded |
| Serial | Not readable — tag corroded |
| Manufacture year | Not readable — tag corroded |
| Age | Unknown — cannot be determined from this tag |
| Configuration | End-suction, close-coupled (visual) |
| |
| Capacity | Not stated — estimated ~700 gpm from loop design (verify) |
| Motor | Tag plate legible: 30 HP · 460V · 3 phase |
| Redundancy | None — sole primary CHW pump; standby pump removed 2016, not replaced |
| Condition note | Seal weepage observed at visit — minor, active |
| Read confidence | 48 / 100 — human review flagged |
| Service & PM details |
| Coupling | Close-coupled — no coupling, belts, or filters fitted |
| Seal | Mechanical seal — active minor weepage; seal kit to be identified and quoted at the outage verification (see recommendation) |
| Bearings | Motor bearings sealed-for-life; pump-end condition unknown pending verification |
Recommendation — verify and document at the next planned outage
This is the documentation gap in the plant's record: a sole-source chilled-water pump — no standby since 2016 — with a corroded tag, an unreadable age, and an active seal weep. None of that says it's about to fail; all of it says nobody can prove it isn't. At the next outage: pull the motor and frame data, check for a casting date code, record the duty point against the loop, and quote the seal kit while it's open. If verification shows a unit of chiller vintage (2009), it joins the years 2–3 chiller window as a planned replacement — planning range $9,000–$13,000 installed, Toledo market, pending verification. Restoring a standby pump position should be priced in the same conversation.
AHU-1 — Trane air handler (production floor)
AST-I010 · Mezzanine mechanical · Serves: Production floor — Lines 1–3 · Status: Operating
Budget replacement · 25 yrs
| Nameplate / spec data |
| Manufacturer | Trane |
| Model | Climate Changer CSAA (built-up, draw-through) |
| Serial | K01F-66318 |
| Manufacture year | 2001 |
| Age | 25 years |
| Coils | Steam heating coil + chilled water coil |
| |
| Capacity | ~24,000 cfm · supply fan 40 HP |
| Fan section | Belt-drive centrifugal · bearings replaced 2022 |
| Casing condition | Panel corrosion at condensate pan; drain pan replaced 2019 |
| Controls | Pneumatic — last pneumatic zone in the plant |
| Read confidence | 85 / 100 |
| Service & PM details |
| Filters | Pre-filters: 24×24×2 pleated, ×12 · Final filters: 24×24×22 bag (8-pocket), ×12 — changed on differential pressure (typically pre 2×/yr, finals 1×/yr) |
| Fan belts | Belt-drive centrifugal fan — matched set of 3 B-section belts; tension checked quarterly, set renewed annually |
| Bearings | Pillow-block fan bearings — greased monthly on the PM route (bearings replaced 2022) |
| Coils | Steam and chilled-water coils chemically cleaned annually, ahead of cooling season |
Recommendation — budget replacement in years 4–5
At 25 years this built-up handler has outlived its casing design life; the corrosion is at the wet section, the coils are original, and it's the plant's last pneumatic control zone — parts and craft knowledge both get scarcer every year. It conditions the production floor, so its replacement belongs in a shutdown window, sequenced last in this plan because the boiler and chiller carry more risk per dollar. Planning estimate for a like-for-like 24,000 cfm air handler replacement (Toledo market, installed, including rigging into the mezzanine, coil and duct tie-ins, and DDC controls conversion): $55,000–$75,000. A coil-and-fan refurbishment alternative should be priced against it in Year 3 — if the casing sections are sound, refurbishment may defer full replacement past the window.
AHU-2 — Daikin air handler (office & QA lab)
AST-I011 · Roof · Serves: Offices and QA lab · Status: Operating
No action — monitor · 10 yrs
| Nameplate / spec data |
| Manufacturer | Daikin Applied |
| Model | Vision CAH (modular, draw-through) |
| Serial | DK16-90427 |
| Manufacture year | 2016 |
| Age | 10 years |
| Coils | Hot water heating coil + chilled water coil |
| |
| Capacity | ~9,500 cfm · supply fan 15 HP, VFD |
| Fan section | Direct-drive plenum fan array |
| Casing condition | Good — no corrosion noted at visit |
| Controls | DDC — on plant BAS |
| Read confidence | 95 / 100 |
| Service & PM details |
| Filters | Pre-filters: 24×24×2 pleated, ×6 · Final filters: 24×24×12 rigid cell, ×6 — changed on differential pressure |
| Drive | Direct-drive plenum fan array — no belts; EC fan motors with sealed bearings, no lubrication required |
| Sensors | QA lab temperature and humidity sensors calibrated semi-annually (see recommendation) |
Recommendation — no action; routine PM
The model citizen: mid-life, on the BAS, clean read, no findings. The QA lab's temperature and humidity stability rides on this unit, so keep its coil cleaning and sensor calibration on schedule — a drifted humidity sensor is a quality finding, not a comfort complaint. Replacement is well beyond the five-year window.
Inspections & compliance
Statutory and insurer inspections for the plant's pressure equipment, plus the ASME CSD-1 controls and safety-device test results for both boilers. Certificate numbers, test dates, and inspector reports are filed against each asset in the plant record — this section is the current-status roll-up.
State & insurance inspections — pressure equipment
| Equipment | Inspection | Inspector / authority | Certificate / report | Last | Next due | Status |
| B-1 boiler (Cleaver-Brooks, 1998) | State boiler certificate inspection | Ohio Division of Boiler Operations | OH-B-1998-4471 | Feb 2026 | Feb 2027 | Current — due first |
| B-2 boiler (Cleaver-Brooks, 2015) | State boiler certificate inspection | Ohio Division of Boiler Operations | OH-B-2015-9032 | Aug 2026 | Aug 2027 | Current |
| Air receiver — AC-1 (240 gal · 200 psi) | State pressure vessel inspection | Ohio Division of Boiler Operations | OH-PV-2005-2210 | Jun 2025 | Jun 2027 | Current |
| Air receiver — AC-2 (200 gal · 200 psi) | State pressure vessel inspection | Ohio Division of Boiler Operations | OH-PV-2019-7784 | Jun 2026 | Jun 2028 | Current |
| B-1 + B-2 boilers | Insurance boiler & machinery inspection | Hartford Steam Boiler Inspection & Insurance Co. | Report HSB-2026-118773 | Apr 2026 | Apr 2027 | Current |
| Air receivers — AC-1 + AC-2 | Insurance boiler & machinery inspection | Hartford Steam Boiler Inspection & Insurance Co. | Report HSB-2026-118774 | Apr 2026 | Apr 2027 | Current |
B-1's state certificate comes due first — February 2027 — ahead of every other pressure-equipment date in the plant, and ahead of the planned replacement outage. The replacement program has to respect that date: either the changeout holds the annual shutdown inside the certificate window, or B-1 goes through a renewal inspection to stay legal while it waits. On the plant's single point of failure, staying current on paper is part of the risk picture, not paperwork trivia — the insurer's April 2026 visit closed with both boilers accepted and no outstanding recommendations.
CSD-1 controls & safety devices — annual test results
ASME CSD-1 testing of boiler controls and safety devices, performed and documented by the plant's boiler service contractor at each annual inspection cycle. Every device on both boilers was tested in 2026; both boilers are compliant.
| Boiler | Control / safety device | Result | Test date | Notes |
| B-1 (Cleaver-Brooks, 1998) | Operating control (pressuretrol) | Pass | Feb 2026 | Cut-in / cut-out verified at 118 / 132 psi |
| B-1 | High-limit control (manual reset) | Pass | Feb 2026 | Tripped at the 145 psi setpoint; reset function verified |
| B-1 | Low-water cutoff (probe type) | Pass | Feb 2026 | Burner trip on simulated low water verified; sensing leg blown down clear |
| B-1 | Safety relief valve | Pass | Feb 2026 | Popped at the 150 psi set pressure and reseated cleanly — but the valve is 2009-vintage: replacement recommended at the next outage on age alone |
| B-1 | Flame safeguard (burner control) | Pass | Feb 2026 | Pilot trial, main-flame trial, and lockout on flame failure all verified |
| B-2 (Cleaver-Brooks, 2015) | Operating control (modulating) | Pass | Aug 2026 | Held header pressure within ±3 psi through a load swing |
| B-2 | High-limit control (manual reset) | Pass | Aug 2026 | Tripped at setpoint; reset function verified |
| B-2 | Low-water cutoff (probe type) | Pass | Aug 2026 | Burner trip verified on slow-drain test |
| B-2 | Safety relief valve | Pass | Aug 2026 | Popped at the 150 psi set pressure; reseated without simmer |
| B-2 | Flame safeguard (burner control) | Pass | Aug 2026 | Purge timing and flame-failure lockout verified |
The paperwork is part of the record
Filter and belt sizes, certificate numbers, and CSD-1 results live in the plant's permanent record alongside the nameplates — so at the next state inspection, insurance audit, or 2 a.m. outage, nobody is hunting a filing cabinet. Audit-ready for the state, the insurer, and the next outage crew.
Capital planning — five-year outlook
Sequenced by production risk, and aligned to planned outage windows so changeouts happen on the plant's schedule instead of the equipment's. Every figure is a planning estimate localized to this plant's own market — Toledo, OH — not a national average and not a quote; actual pricing depends on verified capacity, rigging and tie-in conditions, and contractor bids. See "How these estimates are built" below the table.
| Window | Asset | Action | Planning estimate |
| Year 1 | B-1 (Cleaver-Brooks, 1998) | Replacement engineering + long-lead order; changeout in the annual shutdown. Single point of failure for process steam — the plan's critical path | $190,000–$235,000 |
| Year 1 (same outage) | P-101 (Goulds, 2008) | Wet-end rebuild while the condensate system is drained for the boiler changeout | $6,000–$9,000 |
| Years 2–3 | CH-1 (Trane, 2009) + CT-1 (Marley, 2012) | Chiller replacement in a planned outage; cooling tower fill/basin refurbishment in the same window. Repeat eddy-current test in Year 2 to confirm timing | $168,000–$218,000 combined |
| Years 2–3 (contingent) | P-103 (Armstrong, year unknown) | Verify at next outage first (tag unreadable, seal weeping, no standby). Joins this window as a planned replacement if verification shows chiller-era vintage; price standby restoration with it | $9,000–$13,000 if needed |
| Years 3–4 | AC-1 (Ingersoll Rand, 2005) | Budgeted replacement with a VSD machine; moves earlier only if the original airend forces it | $30,000–$40,000 |
| Years 4–5 | AHU-1 (Trane, 2001) | Budgeted replacement in a shutdown window; price coil/fan refurbishment against it in Year 3 first | $55,000–$75,000 |
| Ongoing | B-2, AC-2, P-102, AHU-2 | Routine PM and inspections only — no capital in the window | PM costs only |
How the per-asset ranges relate to the system's headline figure: MAI's system-calculated five-year capital forecast for this plant is $412,000 — a modeled exposure figure, not a quote and not a simple sum of the rows above. Adding every range end-to-end (including the contingent P-103 line) totals roughly $458,000–$590,000, because the table prices each action as if it happens at full scope, on its own. The system's $412,000 models what the plan actually does: sequences the changeouts across five budget years and two outage programs, probability-weights the contingent items (P-103 replaces only if verification condemns it; AHU-1 may defer on a refurbishment), and nets out work folded into shared outages (the P-101 rebuild riding the boiler shutdown). The two numbers measure different things — modeled five-year exposure vs. the sticker sum of every possible project — and the sequencing is what keeps any single budget year from carrying more than the boiler year.
How these estimates are built
These estimates are localized to the plant's own market — Toledo, OH — because installed mechanical prices follow local labor rates, craft availability, and market conditions; the same boiler carries a different installed price in a different market. The basis: published 2025–2026 installed-cost benchmarks for industrial mechanical equipment (packaged firetube boilers, centrifugal chillers, rotary screw compressors, and built-up air handlers, including rigging, piping and electrical tie-ins, and commissioning; rental bridge equipment and production losses during changeout are excluded), drawn from contractor and industry pricing guides, adjusted by the RSMeans City Cost Index location factor for Toledo mechanical work: index 93.4 against a national average of 100 — a factor of about 0.93, so Toledo mechanical pricing sits roughly 7% below the national average. (For contrast, Detroit's mechanical index in the same RSMeans table is 100.9 — essentially at the national average — which is why estimates are always built for the plant's own market rather than borrowed from another city's job.) Where a nameplate states capacity (B-1: 150 HP; CH-1: 350 tons), the estimate uses it; where it does not or could not be read (P-103), the figure is marked pending verification and sized from the loop's design duty. Estimates prepared October 2026. They are planning figures, not quotes: actual pricing varies with verified capacity, rigging access, outage-window constraints, equipment tier, and contractor bids.
Priority actions
- Start B-1 replacement engineering now. 28 years old, sole source of process steam at full production load, with a tube-sheet watch item already on record. Engineering and long-lead ordering happen while it still runs; the changeout lands in the annual shutdown — a planned outage, not a plant-down emergency with a rental boiler.
- Price the rental-boiler bridge before you need it. Even with a planned replacement, keep a current rental quote and tie-in drawing on file. If B-1 fails early, the bridge is a phone call, not a design project — and it caps the downtime exposure the risk score is flagging.
- Repeat CH-1's eddy-current test in Year 2. The chiller's years 2–3 budget slot should be confirmed by tube condition, not just age. Two tubes are already plugged; the trend sets the date.
- Verify P-103 at the next planned outage. Sole primary chilled-water pump, no standby since 2016, tag corroded, age unknown, seal weeping. Pull casting and motor data, record the duty point, and price the seal kit and the standby restoration while the loop is open.
- Fold the P-101 wet-end rebuild into the boiler outage. The condensate system is drained anyway — the rebuild costs a fraction of an unplanned pump failure during production.
- Put AC-1 in the capital budget for years 3–4. 88,000 hours on an original airend, carrying base plant-air load. A VSD replacement also removes the fixed-speed unloading waste.
- Keep the PM program exactly as documented. Maintenance Maturity 74 is what's keeping a 68-score plant predictable. The plan above assumes inspections, water treatment, and the vibration route keep happening on schedule.
About this report
This is a sample report built on a fictional facility to show the format; in a live engagement, the same report is generated from a field documentation visit — equipment photographs and nameplate data, with AI-assisted extraction (per-read confidence scores shown per asset). It is a planning snapshot, not an engineering inspection, a condition assessment by a licensed engineer, or a quote. Cost figures are planning ranges localized to the plant's own market (Toledo, OH) — built from published national installed-cost benchmarks adjusted by the RSMeans Toledo location factor, as detailed under "How these estimates are built" — and will vary with verified capacity, rigging and outage conditions, and contractor bids. Scores in a live report are MAI system-calculated values from the plant record as of the report date.